Maxwell Air Force Base
Montgomery, ALEnergy Performance
BG partnered with Maxwell Air Force Base–Gunter Annex (MAFB), AFCEC, and DLA on a $37 million energy savings performance contract (ESPC) to improve energy efficiency, resilience, and mission readiness. Using the DOE ESPC procurement vehicle, BG conducted a comprehensive facility assessment and collaborated with MAFB, AFCEC, and DLA to prioritize ECMs addressing critical mission and infrastructure needs.
A key project feature is a 4 MW combined heat and power system, consisting of two 2 MW generators that provide redundancy, reduce reliance on purchased electricity, and allow buildings to operate independently during utility outages. BG also identified 65 buildings totaling 3.27 million square feet for retro-commissioning to modernize outdated controls and improve efficiency, generating approximately $916,800 in annual savings.
The project is expected to save MAFB approximately $111 million over its 21-year performance period while strengthening energy security and supporting the installation’s training mission. Construction is scheduled for completion by March 2028.
Download PDFSize
4.4M sq. ft.
Cost
$37,086,008
Energy Savings
$3.47M first year ($111M over 21 years)
Scope
- Bypass tertiary pumps
- Energy valve installation
- Interior & exterior lighting
- Building envelope
- Hydronic water chemical treatment
- Combined heat & power (CHP)
- Domestic water upgrades
- Flow management device installation
- Retro-commissioning